PROJECT MANAGEMENT FOR ASHLEY CLAIRE DUE 20 MINUTES

PROJECT MANAGEMENT FOR ASHLEY CLAIRE DUE 20 MINUTES

Activity ID Activity Immediate Predecessor Duration in days Resource Work Hours per Day
A Evaluate freezers   2 Alcides 6
B Chart temperatures   6 Joan 4
C Review service record   2 Alcides  
D Consult with HVAC engineer A, B, C 3 Alcides  
E Develop construction plan D 10 Joan  
F Complete IC assignment E 2 Alcides  
G Complete ROI analysis E 5 Joan  
H Conduct regulatory review E 4 Joan  
I Obtain construction approval F, G, H 2 Alcides

WBS Activity Immediate Predecessor Estimated Duration in weeks Resource
1  Process Improvement Project      
1.1  Operational definition      
1.1.1  Research literature   3 Becky
1.1.2  Identify and define terms 1.1.1 1 Ann
1.1.3  Obtain approval of definition 1.1.2 2 Clive
1.2  Target Selection      
1.2.1  Solicit partners for pilot   2 Ann
1.2.2  Hold brainstorming meeting 1.2.1 2 Becky
1.2.3  Identify characteristics of targets 1.2.2, 1.3.1 1 Ann
1.2.4  Obtain approval of partners 1.2.3, 1.1.2, 1.3.4 1 Clive
1.3  Question set      
1.3.1  Identify process group members   2 Clive
1.3.2  Develop question set 1.2.3 4 Ann
1.3.3  Prototype and validate question set 1.3.2 3 Becky
1.3.4  Add partners 1.3.1, 1.2.1 3 Becky
1.4  Pilot process      
1.4.1  Schedule with target audience 1.2.4 2 Becky
1.4.2  Conduct beta test 1.3.4, 1.2.4 2 Clive
1.4.3  Process feedback from target audience 1.4.2 2 Ann
1.4.4  Conduct pilot 1.4.3 2 Clive
1.4.5  Analyze results 1.4.4 2 Clive