Chapter 13 Exercise 4

4. Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate the EACf and the VACf. Based on your data, what is your assessment of the current status of the project? At completion?

C:\Users\1058960132C\AppData\Local\Microsoft\Windows\INetCache\Content.Outlook\14052ZYK\media_c24_c24ed22d-5630-4e4c-b274-e7aadfbd5a73_phplmKIiT.png

C:\Users\1058960132C\AppData\Local\Microsoft\Windows\INetCache\Content.Outlook\14052ZYK\media_32c_32c22d09-4e03-4e55-99a1-a94948faaad0_phpn7KRDt.png

C:\Users\1058960132C\AppData\Local\Microsoft\Windows\INetCache\Content.Outlook\14052ZYK\media_0a9_0a9646b4-6e48-43f0-a18c-4562f2c7a3df_phpM2KZUN.png

Chapter 14 Exercise 4

What are some of the lessons learned from a recent project in your organization? Was a retrospective done? What action plans were generated to improve processes as a result of the project?